The Operations and Control window for solar displays the data related to power generation, power transmission, and weather overcast.

OperationsControl

The solar panels are grouped into blocks, for example, Block 1, Block 2, and so on. The String Current (A) indicator has different colors for different power value. The solar panels are represented with different shades based on the power generated.

  • Expand Operations_and_Control dropdown to navigate to Blocks, Main Substation, and Main Transformer window.

    OP dropdown

Navigating Operations and Control for Solar

The following sections provide information on how to navigate and view details about each of the blocks:

Blocks

  1. Select Blocks to view block level monitoring.

    The Solar – Block Level Monitoring window displays the details of each block such as Central Inventor, SCB status, String, Panel, Availability, Average Irradiance, DC Output, AC Output, and Total Energy.

    Embedded Image (65% Scaling) (LIVE)

  2. Select Central Inverter on any of the Blocks to view the performance analysis.

    The Solar – Central Inverter Performance Analysis window is displayed.

    OC block performance

  3. The SCB Status in the Solar – Block Level Monitoring window indicates the performance and health status of each block. Select SCB Status on any of the blocks to view the performance analysis of the selected string combiner box.

    The Solar – String Combiner Box Performance Analysis window is displayed.

    SCB performance

  4. Select any of the String No. in the Solar – String Combiner Box Performance Analysis window to view string monitoring.

    The Solar – String Monitoring window appears.

    String monitoring

  5. From Solar – String Monitoring window, select any of the solar panel to view the status.

    The Solar – Panel Performance Analysis window appears.

    PV003

Main Station

  1. Select Main_Substation to view block level monitoring.

    The Solar – Sub Station Performance Analysis window displays the details of each sub station under each Main station.

    Substation

  2. Select Power_Monitoring to view the details about energy and power that each generated in each sub station.

    The Solar – Sub Station Performance Analysis window displays the details of the power generated.

    Power monitoring

    Main Transformer

    1. Select Main_Transformer to view block level monitoring.

      The Solar – Transformer Performance Analysis window displays the details of each transformer.

      Transformer

      Related Links