Plant SCADA

Integration Report Summary tab

  • Last UpdatedNov 03, 2026
  • 2 minute read

The Integration Report Summary tab provides an overview of the import process performed by the Integration Assistant.

It includes the following Project Details.

Project detail

Description

Plant SCADA Project Name

The name of the source Plant SCADA project.

Status

Indicates if the import process was successful and if any warnings were detected.

Date/Time

When the import process started.

Plant SCADA Backup File

The CTZ file that was used to initiate the import process.

Plant SCADA Compiler Version

The version of Plant SCADA that was used to compile the imported project.

[General]TagStartDigit

Indicates the setting for the Plant SCADA parameter [General]TagStartDigit at the time of import.

If set to zero (0), tags, tag items, and equipment names that have a number as a first digit will not be supported.

System Platform Galaxy Name

The Galaxy that hosts the imported content.

Templates Imported

A tally of the number of templates that were imported. For more information, see Integration Report Templates Tab.

Instances Imported

A tally of the number of equipment instances that were imported. For more information, see Integration Report Instances Tab.

Import Duration

The length of time taken to complete the import process.

Connectivity Scope Names

This is used to establish communications between Application Server and Plant SCADA. It represents a combination of the Plant SCADA project name and the clusters included in the project.

In Application Server, this name is included at the start of any Plant SCADA tag names for the Read from / Write to property on an attribute's I/O feature.

Analysis Report Name

The name of the Project Analysis Report that was created before the import process began.

The Integration Assistant Options Selected section includes a summary of the configuration settings that were applied to the Integration Assistant when it was run. For more information about these settings, see Run the Plant SCADA Integration Assistant.