Commitment change line items
- Last UpdatedSep 12, 2024
- 7 minute read
If the template from which a communication was created is not configured as Expenditure but is configured to include financial values as required or optional, these values are treated as commitment change values.
If the contract does not have line items, only a single commitment change financial value can be specified for each communication. See Commitment change values.
If the contract has line items defined, multiple commitment change values can be specified for a communication. Each proposed change applies to a different line item and will affect its approved commitment value once the communication (or if necessary, its successor) has been approved/agreed.
Changes can also be proposed for the budget values of discrete pro rata progress measures, with any associated apportioned progress measures on other line items updated accordingly.
Only users with Contractor Representative and Contractor Administrator contract roles can view, add and edit financial values.
Add commitment changes to line items
The communication must be in a Draft state to add commitment changes to contract line items.
To add a commitment change to a contract line item:
-
On the Communication Details page, click the Change tab.
-
Click Add Change.
The Add Change to Line Item dialog box is displayed.
-
In the Line Item box, start to type the Line Item Code, Supplementary Code or Title of the line item you want to propose a change to.
Line items which match your text are displayed.
-
Click the line item you want to propose a change to.
-
Enter the following required information:
-
Unit Rate line items: Proposed Quantity Change
-
Progressive Payment, Milestone Payment, Lump Sum and Reimbursable line items: Proposed Commitment Change (in the line item currency)
The Revised Commitment value is automatically updated.
-
-
If you selected a line item which records progress in one or more Discrete Pro Rata progress measures, you can also propose changes to the budgets of the progress measures.
Click the Change field for the progress measure and enter the value of the change. The Revised value is automatically updated.
Warning If you enter a value which means that the revised budget will be lower than the progress already consumed, the field is shown in red and you cannot move away from the field until you correct the value.
-
Click Save and Continue to add the proposed change and clear the fields so you can add another one.
Alternatively, click Save and Close to add the proposed change and close the window.
Warning If you try to add a commitment change to a line item which has already been added to the communication, an error message is displayed. Edit the commitment change instead - see Editing Commitment Changes to Line Items below.
The commitment change is displayed on the Change tab.
See Commitment change values for information about adding single commitment change values.
View commitment changes to line items
The commitment changes to line items are displayed on the Change tab. The total Financial Impact of the communication is also displayed on the Communication Details page.The line items are grouped by breakdown item (if relevant), and any progress measures which have proposed budget changes are shown beneath their parent line item.
On this page, you can:
-
Expand and collapse the grouping rows for breakdown items and line items.
-
Filter the items by typing part of one of the following:
-
Breakdown item code or title
-
Line item code, supplementary code, name or control account code
-
Progress measure title
Click the
button to expand the search box, and type the search text.
-
-
Move through the pages of displayed items, and change the number of items displayed per page, by clicking the paging buttons.
-
Export a list of proposed changes by clicking the
Export button.
The breakdown item code and title, if relevant, are shown in the breakdown item row.
|
Field |
Description |
|
Code |
The line item code. |
|
Title |
The name of the line item that the commitment change applies to. |
|
Line Item Type |
The type of line item. |
|
Control Account Code |
The code of the control account that the line item is associated with. These are defined for the project/department (see Control Accounts). |
|
Supplementary Code |
The supplementary code of the line item. |
|
¤ (Currency) |
The currency of the line item. |
|
Consumed |
Progress measures only. The budget of the progress measure that has already been consumed in progress communications. |
|
Current |
|
|
Change |
|
|
Revised |
The new value once the communication (or if necessary, its successor in a process chain) has been approved/agreed, equal to Current + Proposed Change.
|
See Commitment change values for information about viewing single commitment change values.
View the details of commitment changes to line items
Users with the following contract roles can view the details of proposed commitment changes on the Change tab:
-
Contractor Representative
-
Contractor Administrator
To view the details of a proposed commitment change, click its row on the Change tab. The View Change to Line Item dialog box is displayed.
|
Column |
Description |
|
Line Item Type |
The type of line item: |
|
Breakdown Item Name |
Only displayed if breakdown items have been configured for the contract. The name for the contract breakdown item that the line item is associated with. |
|
Line Item Code |
The code of the line item. |
|
Line Item Title |
The title of the line item. |
|
Line Item Supplementary Code |
An additional code which can be used to identify the line item. |
|
Line Item Currency |
The currency of the line item. |
|
Unit of Measure |
Unit Rate line items only. The unit of measure of the line item. |
|
Current Commitment |
The current commitment value of the contract line item, in the line item currency. Unit Rate line items: Equal to the current committed quantity x the unit price of the line item. Note This is the value at the time the communication was approved/agreed. |
|
Proposed Quantity Change |
Unit Rate line items only. The proposed change to the quantity of the line item. |
|
Proposed Commitment Change |
Progressive Payment, Milestone Payment, Lump Sum and Reimbursable line items only. The proposed change to the value of the line item, in the line item currency. |
|
Revised Commitment |
The new commitment value of the contract line item once the communication (or if necessary, its successor in a financial link) has been approved/agreed. Unit Rate line items: equal to the revised quantity x the unit price of the line item. Progressive Payment, Milestone Payment, Lump Sum and Reimbursable line items: equal to Approved Commitment + Proposed Change. |
If the line item records progress in one or more Discrete Pro Rata progress measures, proposed changes to the budgets of the progress measures are also shown.
|
Field |
Description |
|
Title |
The title of the progress measure. |
|
Affects Other Line Items |
Indicates if the progress measure is linked to an Apportioned progress measure on another line item and will therefore affect the values for that line item. |
|
EAC |
Estimate at Completion. The estimate of how much work is represented by the progress measure. |
|
Consumed |
The budget of the progress measure that has already been consumed in progress communications. |
|
Budget |
The current budget value of the progress measure. |
|
Change |
The value of the budget change applied to the progress measure. |
|
Revised |
The new budget value of the progress measure once the communication (or if necessary, its successor in a financial link) has been approved/agreed. Equal to Budget + Change |
Edit commitment changes to line items
You can only edit commitment change values for a communication if it is in a Draft state.
To edit a commitment change value recorded for a line item from a communication:
-
Click its row on the Change tab. The View Change to Line Item dialog box is displayed.
-
Click the
Edit button. The dialog box is refreshed as the Edit Change to Line Item dialog box.
-
Edit the following required information:
-
Unit Rate line items: Proposed Quantity Change
-
Progressive Payment, Milestone Payment, Lump Sum and Reimbursable line items: Proposed Commitment Change (in the line item currency)
The Revised Commitment value is automatically updated.
-
-
If you selected a line item which records progress in one or more Discrete Pro Rata progress measures, you can also propose changes to the budgets of the progress measures.
Click the Change field for the progress measure and enter or edit the value of the change. The Revised value is automatically updated.
Warning If you enter a value which means that the revised budget will be lower than the progress already consumed, the field is shown in red and you cannot move away from the field until you correct the value.
-
Click Save.
The updated change is displayed on the Change tab.
See Commitment change values for information about editing single commitment change values.
Remove commitment changes to line items
You can only remove commitment change values from a communication if it is in a Draft state.
You cannot remove a budget change for a progress measure independently but must remove all changes that apply to the line item.
To remove a commitment change value recorded for a line item from a communication:
-
In the Commitment Changes section of the Communication Details page, click
Delete for the commitment change value you want to remove.
A confirmation message is displayed.
-
Click OK.
The commitment change value is removed from the communication.
See Commitment change values for information about removing single commitment change values.