AVEVA™ Contract Risk Management - Contractor Portal

Progress communications

  • Last UpdatedSep 12, 2024
  • 6 minute read

Certain types of line items require their progress to be measured and recorded, so that the appropriate payment can be claimed and made against them. Once the appropriate progress measures have been configured for line items, progress against them can be recorded in progress communications.

Progress communications can only be Contractor to Company communications.

Progress is recorded on a communication once it has been created and saved. To record progress on a communication, the following conditions must be met:

  • The communication's template is configured to record progress but not expenditure.

  • The contract has line items which have associated progress measures.

  • The communication is in Draft state.

The budget of discrete pro rata progress measures can be updated through a change communication - see Commitment change line items.

Note Related communications cannot be created from progress communications. You can only create links to progress communications by selecting them when creating a expenditure communication that also records progress. Only Approved/Agreed progress communications which have not already been claimed can be selected.

View recorded progress

All users with contract roles can view the progress recorded against a communication.

To view the progress recorded against on a communication:

  1. On the communication register, click the Title of the communication you want to view the recorded progress for.

    The Communication Details page is displayed.

  2. Click the Progress tab.

    If you can claim for progress on the communication (you have the correct contract role and the communication is editable, the All Available Progress Measures filter is auto-selected from the drop-down list so that all the possible discrete progress measures which you can claim for are displayed.

    Otherwise, the All Claimed Progress Measures filter is displayed by default and All Available Progress Measures is not available.

    The progress measures are grouped by breakdown item and line item, sorted alphabetically by breakdown item reference and then line item code.

    You can also select All Claimed Progress Measures to see the progress measures that have been claimed for in this communication. If any discrete progress measures which are associated with apportioned progress measures have been claimed for, the apportioned progress measures are displayed with this filter.

On this page, you can:

  • Expand and collapse the grouping rows for breakdown items and line items.

  • Filter the progress measures by typing part of the breakdown reference or name, line item code or title, or progress measure title. Click the fa-search button to expand the search box, and type the search text.

  • Move through the pages of displayed items, and change the number of items displayed per page, by clicking the paging buttons.

  • Export a list of claimed progress measures for the All Claimed Progress Measures filter only, by clicking the fa-download Export button.

    The values displayed on the Progress tab are explained in the following table.

    Column

    Description

    Breakdown item reference and name

    Grouping row.

    Only displayed if breakdown items have been configured for the contract. The reference and name of the contract breakdown item that the progress measure's parent line item is associated with.

    Line item code and title

    Grouping row.

    The code and title of the progress measure's parent line item.

    Progress measure title

    The title of the progress measure.

    Budget

    The budget of the progress measure.

    Weighting

    The weighting value of the progress measure, as a percentage of the total line item commitment.

    To Date / EAC

    Estimate at Completion. The contractor's estimate of how much work is represented by the progress measure, before any updates made in this communication.

    Once the communication has been approved or agreed, the To Date values displayed on this communication will not change even if there are further updates to the progress measure.

    To Date / Claimed

    The amount claimed against the progress measure, before any updates made in this communication.

    Once the communication has been approved or agreed, the To Date values displayed on this communication will not change even if there are further updates to the progress measure.

    Current / EAC

    Estimate at Completion. The update in this communication to the contractor's estimate of how much work is represented by the progress measure.

    Current / Claimed

    The amount claimed in this communication against the progress measure.

    Cumulative Claimed

    The total of the To Date and Current values of the amount claimed against the progress measure.

    Once the communication has been approved or agreed, the Cumulative Claimed value displayed on this communication will not change even if there are further updates to the progress measure.

Record progress on a communication

Users with the following contract roles can record progress against a communication:

  • Contractor Representative

  • Contractor Administrator

To record progress against a communication or update the Estimate at Completion:

  1. On the communication register, click the Title of the communication you want to record progress against.

    The Communication Details page is displayed.

  2. Click the Progress tab.

    Make sure the All Available Progress Measures filter is selected from the drop-down list so that all the possible discrete progress measures which you can claim for are displayed.

  3. Click the fa-search button to expand the search box, and type the search text for the progress measure you want to claim for. You can search by breakdown code or name, line item code or title, or progress measure title.

    Progress measures which match your text in any of these fields are displayed.

  4. If necessary, scroll across the page so that the This Period columns are visible.

  5. To update the Estimate at Completion value of the progress measure, enter the new value in the This Period / EAC column for the progress measure.

  6. In the This Period / Claimed column for the progress measure, claim for the progress measure as follows:

    • Discrete Pro Rata: Enter the amount of progress in this period. This value is in the unit of measure/currency of the line item

      Warning If you enter an invalid value or if the value claimed will exceed the Budget of the progress measure, the field is shown in red and you cannot move away from the field until you delete or correct the value.

    • Discrete Weighted Milestone: Select the check box. If the progress measure has already been claimed, you cannot select it.

  7. Press Enter or Tab, or click on another area of the page to update the value you are claiming for.

    If you claim for progress, the Cumulative Claimed value is updated.

    Edit updates to progress measures

    You can only edit updates to progress measures if the communication is in Draft state.

    Users with the following contract roles can edit the updates to progress measures.

    • Contractor Representative

    • Contractor Administrator

    To edit updates to progress measures:

    1. On the Progress tab, make sure the All Available Progress Measures filter is selected from the drop-down list so that all the possible discrete progress measures which you can claim for are displayed.

    2. If necessary, scroll across the page so that the This Period columns are visible.

    3. To update the Estimate at Completion value of the progress measure, enter the new value in the This Period / EAC column for the progress measure.

    4. In the This Period / Claimed column for the progress measure, update the progress measure as follows:

      • Discrete Pro Rata: Enter the amount of progress in this period. This value is in the unit of measure/currency of the line item

        Warning If you enter an invalid value, the field is shown in red and you cannot move away from the field until you correct the value.

      • Discrete Weighted Milestone: Select or clear the check box.

    5. Press Enter or Tab, or click on another area of the page to update the value you are claiming for.

      If you claim for progress, the Cumulative Claimed value is updated.

      Remove updates to progress measures

      You can only remove updates to progress measures from a communication if the communication is in Draft state.

      Users with the following contract roles can remove updates to progress measures from a communication:

      • Contractor Representative

      • Contractor Administrator

      To remove an update to the progress measure's Estimate at Completion from a communication, clear its value or click the fa-times icon in the Current / EAC column on the Progress tab.

      To remove recorded progress from a communication, clear its value or click the fa-times icon in the Current / Claimed column.