Commit configuration changes
- Last UpdatedDec 12, 2025
- 2 minute read
After you make a change to the database (for example, add a tag), you must commit the change to the AVEVA Historian system. All database changes are immediately implemented. However, database modifications are not applied to the system until you commit them. You are committing the changes to the system, not the database.
The system reconfigures itself with no interruption for unaffected objects in the database.
Changes cannot be committed:
-
During the first five minutes after starting the Historian.
-
During the creation of a new data block because of a prior change.
For more information, see Dynamic configuration in the AVEVA Historian Concepts Guide.
To commit configuration changes to the system:
-
In the Operations Control Management Console, expand a server group and then expand a server.
-
Right-click Configuration Editor (or any sub-items in the console tree) and then click Commit Pending Changes. The Commit Pending Changes - Confirmation dialog box appears.

-
To view a list of the pending changes, click Display.

Column descriptions are as follows:
Object Type
Used to indicate the type of object to which the modifications apply.
Status
Used to indicate the type of modification.
Object Key
The unique identifier of the modified object. If the modified object is a system parameter, the value will be 0. For all other object types, the value is from one of the following tables and columns: IODriver.IODriverKey; IOServer.IOServerKey; Topic.TopicKey; Tag.wwTagKey; StorageLocation.StorageType; SnapshotDetail.StorageSize.
Item
The key identifier for the column modified in the table. For example, TagName for the Tag table, Name for the Topic table, and so on.
-
To commit the outstanding changes, click Commit.
-
An information box appears, showing the status of the reconfiguration.
-
Click OK.