OEE Use and Bottlenecks

  • Last UpdatedMar 22, 2016
  • 1 minute read

The following time chart shows the OEE Use durations for the utilization events that are pertinent to the OEE calculations. It also shows which entities were bottlenecks and for what time periods (for example, the Packer was the bottleneck entity from 6 to 7 am).

A time chart shows the OEE use durations for the utilization events that are pertinent to the example OEE calculations.

Note the following about the chart:

  • Bottleneck time periods that are pertinent to OEE calculations are shown in dark gray with the label "Bottleneck."

  • Bottleneck time periods that are not pertinent to OEE calculations are shown in lighter gray with the label "BN-Not in OEE." For example, Filler1 was considered as a bottleneck entity from 7 to 8 am. However, it had an OEE Use designation of Neither (that is, not in Runtime or Downtime), so it was not included in OEE calculations during this time period.

  • Filler3 is not considered as a bottleneck entity when the other two Filler entities are because it is configured to not be enabled during Downtime. The same is true for Sleever2.