Define the Process Trains
- Last UpdatedOct 25, 2024
- 1 minute read
After you define the process model, you must define the process trains. Process trains are lines of production that are assigned to scheduled batches. A train can contain one or more units, and a unit can be part of multiple trains.
To define process trains
-
On the Environment Display dialog box, double-click the TrainEdit
icon.
The Train Editor dialog box appears.
-
In the Name box, type the first train name shown in the table that follows.
-
Click Add.
-
On the Units area, click Assign Units.
The Assign Units to Train dialog box appears.
-
Select the appropriate Assigned Units shown in the table that follows.
-
Click Apply or OK as appropriate. Remember that Apply does not close the dialog box.
-
Close the dialog box.
Train Name
Assigned Units
Mixer 1 Train
Bulk1, Bulk2, Hold1, Mixer1
Mixer 2 Train
Bulk1, Bulk2, Hold2, Mixer2
The following image shows an example of the entries for Mixer 1 Train.