Scenario 1

  • Last UpdatedMay 17, 2023
  • 1 minute read

Assume work order ABC is created from process P1 to make item I1, production is reported from the job for operation 10 with a reason code of R1, and the following dynamic routing parameters are set to No:

  • Redo job originating dynamic routing at end of dynamic process

  • Use label in dynamic routing work order or operation IDs

  • Combine dynamic routing from the same operations of different work orders

  • Copy remaining jobs to end of WO created for dynamic routing

The result is as follows, because the first row of the row of the dynamic routing usage table applies:

The dashed line represents the actual flow of the material to be reworked, though it will not appear on a routing diagram for either work order. The "1" for the identifier of the new work order assumes no other automatically-generated work orders have previously been created.