Understand intermediate operation production
- Last UpdatedOct 28, 2024
- 1 minute read
The Add Production dialog lists all incomplete serial numbers at the entity running the job or at its parent entity for the produced item. If a job is hard pegged, you can see the serial numbers produced for a work order to which the job is associated. You can see the serial numbers that are complete for an operation but you cannot see the list of incomplete serial numbers. This does not include serial numbers that are consumed in a downstream operation.
If the job BOM storage locations are defined as the downstream entity for the next operation or its parent for each operation in the route, the produced serial numbers are transferred by default to the entity that is scheduled to run the next job in the work order.
If the serial numbers are not stored at the entity or its parent entity on which you are running a job, you must use the Transfer Serial Numbers button to manually transfer the produced serial numbers to the current job location.