A project can be saved as a single package (.pkg) file. This file can then be selected when creating a project. The new project is then created with all the data and settings of the packaged project. Refer to the Installation guide for more information on creating projects.
To package a project:
-
Select Project > Package Project.
-
Packaging a project requires certain SQL Server Management Objects (SMO) to be installed and available. If any of these are not installed the following message is displayed:

Click on the links to download the objects, and then install them from the downloaded .msi files.
Once the SMOs have been installed, select Project > Package Project again.
-
The Project Packager window is then displayed:

-
Select the location that the package file is to be saved to by clicking the ... button. The following window is then displayed:

-
Browse for the required location, enter the file name in the File name field, and click Save.
-
The selected location and file name are then displayed in the Output file field of the Project Packager window:

-
Click OK to start packaging the project.
-
The process of the packaging is then displayed in the window. For example:

-
Click Cancel to stop the process at any time.
-
When packaging is complete, the following message is displayed:

-