Edit properties for an active production run

  • Last UpdatedApr 22, 2022
  • 2 minute read

If an active production run's duration is less than 48 hours, you can edit its production run and OEE data properties. This allows you to correct mistakes or change the planned duration of a production run.

Note that changing the Ideal Production Rate property will recalculate the Performance KPI and update the production run's hourly tag data for the 3 most recent hours. Equipment efficiency tag data is updated at the top of every hour.

To edit production run properties

  1. Select the The Edit button icon below the production run control.

    Selecting Edit

    The Edit a Production Run dialog appears.

    The Edit a Production Run dialog

    Note that the OEE data property values shown here will be those that were entered when the production run was started or last edited and not the latest values entered on the OEE Data Properties tab.

  2. Edit the production run and OEE data properties.

  3. Select Save.

    The data that appears on the Production Events and OEE Data Properties tabs is updated to reflect the property changes.