Steam distribution systems found in refineries and large petrochemical complexes are complex and highly integrated systems with multiple pressure levels. The objective of this simulation is to:
-
Provide a steam balance to show the steam generation required to satisfy the electrical power demand and the process steam consumption.
-
Size piping to meet steam delivery pressures at the steam consumers.
-
Validate the process control strategy by showing how the controls respond in the event of an upset, such as a trip of a steam turbine.