AVEVA™ Production Management

Modify Planning records in the Planning Schedule chart

Modify Planning records in the Planning Schedule chart

  • Last UpdatedApr 23, 2025
  • 2 minute read

You can view Planning records in a visual chart to help you see when activities are scheduled. You can drag the bars to edit the planned times, and save or cancel planned events.

Planning schedule chart with a column of activity IDs and corresponding Gantt bars spanning Tuesday and Wednesday.

You can select multiple items in the Planning chart, by holding the Control key while selecting bars. The corresponding records in the Results grid will display highlighting.

To modify Planning records in the Schedule view

  1. Change to the Planning module, then view the Planning Schedule chart.

  2. Click a bar in the Schedule chart to stretch the bar to change the planned start and end times.

    Note You can change the order of planned records by changing order of records in the grid view. See Reorder the chart bars in the Planning Schedule chart.

  3. When the schedule is correct, select Save Changes.

    Planning schedule chart with a column of activity IDs and corresponding Gantt bars spanning Tuesday and Wednesday. A green bar appears on top of the blue gantt which indicates that an actual record event occurs.

    Note When the Actual record event occurs, this event shows as a green bar on the Schedule chart.

    If planned events overlap in time, the bars in the chart turn red to indicate a time overlap.

    Planning schedule chart showing an Activity ID column and Gantt bars in red, blue, and dark red. A green bar appears on top of a third Gantt bar to indicate an actual recorded event. Red bars indicate overlapping times.

    You can still modify the end time of a planned event after the Actual event has started.