AVEVA™ Contract Risk Management - Company Portal

Edit schedule item actual dates

  • Last UpdatedDec 19, 2024
  • 1 minute read

The following users can edit the actual start and end dates of completed schedule items if they also have the Edit Schedule Item Actual Dates permission:

  • Tender administrators.

  • Any tender team member assigned to the schedule item.

To edit the actual dates of a schedule item:

  1. Navigate to the home page of the tender. If necessary, click the Schedule tab.

  2. Click the fa-sort-down drop-down arrow for the schedule item, and select Edit Actual Dates from the menu.

    The Edit Actual Dates page is displayed.

  3. Update the Actual Start Date and Actual End Date as required.

    The end date must be later than the start date.

  4. Select Save.