Version 4​.0 metrics definitions

  • Last UpdatedFeb 25, 2025
  • 2 minute read
  • Answered Tasks – All Tasks that have Values associated with them for the specific Procedure Instance

  • Total Tasks – Sum total of tasks that could or were answered for the specific Procedure Instance

    • Includes all "Active" Tasks

    • Includes all "Active & Expected" Tasks

    • Includes all "Inactive" Tasks that have answers associated

  • Extra Tasks – Sum total of tasks that have a value of "answered" but do not have a State of "Active & Expected"

    • Includes Active Tasks that are Answered

    • Includes Inactive Tasks that are Answered

  • Percent of Active & Expected Tasks - Number of Answered "Active & Expected" Tasks divided by the number of "Active & Expected" Tasks

  • Percent of Total Tasks – This metric will closely match the current Version 3.2 metric for Procedure completion and will be used primarily as a bridging metric to compare with work processes completed in Version 3.2 and 4.0

    • Active & Expected that are Answered  Total of "Active & Expected" + "Active" + "Inactive" that are Answered.

Version 4.0 Example 1:

  • Procedure has 100 actual Tasks divided between 2 pieces of equipment

  • User answers 45 tasks for the one piece of equipment who’s status was "Online", the other 50 tasks are disabled by status selection of "Offline"

  • When the Supervisor runs a report on this procedure he is shown the following:

    • Answered Tasks = 45

    • Total Tasks = 100

    • Extra Tasks = 0

    • Percent of Active & Expected Tasks = 90%

    • Percent of Total Tasks = 95% ((45+50) 100) (Version 3.2 Metrics)

Version 4.0 Example 2:

  • Procedure has 100 actual Tasks divided between 2 pieces of equipment

  • User answers 45 tasks for the one piece of equipment whose status was "Online" and answers 5 tasks for the group that was disabled by the Group status selection of "Offline"

  • When the Supervisor runs a report on this procedure he is shown the following:

    • Answered Tasks = 50

    • Total Tasks = 100

    • Extra Tasks = 5

    • Percent of Active & Expected Tasks = 90%

    • Percent of Total Tasks = 95% ((45+50) 100)