Please ensure Javascript is enabled for purposes of website accessibility
Powered by Zoomin Software. For more details please contactZoomin

AVEVA Pipeline Operations for Liquids

Define the On-Peak Times

  • Last UpdatedJul 04, 2024
  • 1 minute read

The purpose of the On-Peak Times on the On/Off Peak Configuration tab of the pumpstation Row Edit dialog is to assign on-peak times to the days of the week. There can be two periods for each day of the week where on-peak rates apply.

  • Each row number matches a particular day of the week (for example, day 0 is Sunday). The row numbers and corresponding days of the week are documented in the table below.

  • Each period is defined by a start time and stop time. The stop time must be greater than the start time.

  • The times for a period may be left blank. In this case, the period is ignored.

  • Times may be in the format HH:MM:SS or HH:MM.

    Row Number

    Day of the Week

    0

    Sunday

    1

    Monday

    2

    Tuesday

    3

    Wednesday

    4

    Thursday

    5

    Friday

    6

    Saturday

To define On-Peak Times

  • Enter the Start Time and Stop Time using either of the following formats:

    • HH:mm:ss

      OR

    • HH:mm