Rule One
- Last UpdatedJan 23, 2023
- 1 minute read
When a cable is routed from or to:
|
1 |
Source connection, equipment or electrical connection |
|
2, 4, 6, 8 |
Entry into a cableway. |
|
3, 5, 7, 9 |
Exit from a cableway. |
|
10 |
Destination connection, equipment or electrical connection. |
Note:
When connected to equipment, elconn may not have a direction.

The cable will have a minimum straight length in the same direction as the connection point:
-
If the cable has a bend radius greater than 0, then the bend radius for a metric project is plus 10mm or 1/2" for an imperial project.
-
If the bend radius is equal to 0, then the bend radius for metric project is 100mm or 4" for an imperial project.