Split a PO position

  • Last UpdatedMay 07, 2026
  • 1 minute read

Split a Purchase Order (PO) position into two separate PO positions. The new PO position contains the same material, related attachments, technical material requisition information, and request for quote information as the original PO position. Initially, the required quantity for the new PO position is set to 0. You can manually distribute the required quantity between the two PO positions.

You can split a PO position when a part of the material quantity requires different handling. For example, if one supplier cannot deliver the full quantity or meet the delivery deadline, you can split the PO position into two: one position for the quantity delivered by the original supplier and another position for the quantity delivered by a different supplier.

  1. Navigate to the s50018 Purchase Order screen.

  2. To refresh the screen, select the F5 key.

  3. In the Purchase Order Header grid, select a row.

  4. In the Position grid, select the Purchase Order Position tab.

  5. In the Purchase Order Position grid, select a row.

  6. On the Home menu, in the Add positions group, select Split position.

    In the Purchase Order Position grid, a copy of the selected PO position is created.

  7. Select the new PO position, select the General tab, in the Quantity field, enter the required quantity.

    You can manually distribute the required quantity between the two PO positions that you split.

  8. (Optional) Enter the relevant details in other fields as required. For more information on all the fields, see s50018 Field descriptions.

  9. To save the changes, on the Home menu, in the Record group, select Save.