To copy a screen layout from a source project to a target project, ensure a role is assigned access to the layout in the single project mode. For more information, see Assign a role access for a layout in the single project mode.
-
Navigate to the s00064 Screen Management screen.
-
To refresh the screen, select the F5 key.
-
In the Screens grid, select a row.
-
Select the Layouts tab, in the Layouts grid, select a row.
-
On the s00064 menu, in the Layout Actions group, select Copy layout to Project.
The d0213 Copy Layout to Project dialog appears.
-
From the From Project dropdown, select the ID of the source project.
-
From the To Project dropdown, select the ID of the target project.
-
Select Ok.
In the Single Project Mode tab, in the Roles using layout in Single Project Mode grid, a new copy is created.
-
(Optional) Enter the relevant details in other fields as required. For more information on all the fields, see s00064 Field descriptions.
-
To save the changes, on the Home menu, in the Record group, select Save.