Update the milestone dates of a VDS

  • Last UpdatedMay 07, 2026
  • 1 minute read

Update the milestone dates of a Purchase Order (PO) related to a Vendor Deliverable Schedule (VDS).

  1. Navigate to the s51009 Vendor Deliverables Schedule screen.

  2. In the Current Project control block, from the Project dropdown, select the required project ID.

  3. To refresh the screen, select the F5 key.

  4. In the Vendor Deliverables Schedule grid, select a row.

  5. On the s51009 menu, in the Actions group, select Milestone Dates.

    The d0171 Milestone Dates dialog appears.

  6. Perform the following:

    • From the Stage 1 dropdown, select the stage 1 milestone date related to the PO items.

    • From the Stage 2 dropdown, select the stage 2 milestone date related to the PO items.

    • From the Stage 3 dropdown, select the stage 3 milestone date related to the PO items.

      The names of the Stage 1, Stage 2, and Stage 3 milestones are updated based on the milestone names defined for the PO in the s40005 Milestones screen.

  7. Select Calculate Due Dates.

    The due dates are calculated for the documents related to the milestones for the selected PO.

    In the Vendor Deliverable Schedule grid, in the Document Status tab, in the First Approval Cycle section, the Due Date field is updated.