s52004 Field descriptions
- Last UpdatedMay 07, 2026
- 4 minute read
Common fields in the screen
|
Field |
Description |
|---|---|
|
SI |
Status Indicator: Indicates the status of a record related to validation errors, warnings, and updates. |
|
Defined By |
The ID of a user who created a record. |
|
Defined At |
The date and time when a record was created. |
|
Updated By |
The ID of a user who updated a record. |
|
Updated At |
The date and time when a record was updated. |
Inspector/Co-ordinator control block
|
Field |
Description |
|---|---|
|
Inspection coordinator |
The name of an inspection coordinator assigned for an inspection visit. |
|
From date |
The date from when an inspection visit is scheduled. |
|
To date |
The date until when an inspection visit is scheduled. |
Inspection Visits grid
|
Field |
Description |
|---|---|
|
Project |
The ID of a project related to an inspection visit. |
|
Pur No |
The ID of a Purchase Order (PO) related to an inspection visit. |
|
PO Title |
The title of a PO related to an inspection visit. |
|
Visit ID |
The ID of an inspection visit related to a PO. |
|
Description |
The description of an inspection visit. |
|
Status |
The status of an inspection visit. |
|
Forecast Inspection Visit |
The forecast date when an inspection visit is dispatched by a supplier. |
|
Actual Inspection Visit |
The actual date when an inspection visit is carried out. |
|
Inspection coordinator |
The name of an inspection coordinator assigned for an inspection visit. |
|
Inspection Address |
The inspection address where the inspection is carried out. |
|
Inspection Agency |
The name of an inspection agency related to an inspection visit. |
|
Inspector |
The name of an inspector who physically carries out an inspection visit. |
|
Release |
Indicates an inspection visit is for release. If the Release checkbox is selected, then you cannot allocate the items to another release inspection visit unless a Non-Release Certificate is issued. |
|
Man-hour forecast |
The forecast hours required for an inspection visit. |
|
Man-hour actual |
The actual hours recorded for an inspection visit. |
The following table describes the fields in the Inspection Visit Notes tab.
|
Field |
Description |
|---|---|
|
Inspection Visit Notes |
The comments related to an inspection visit. |
The following table describes the fields in the Visit Items tab.
|
Field |
Description |
|---|---|
|
Project |
The ID of a project related to an inspection visit. |
|
PO Position |
The sequence number of an expediting position in a Purchase Order (PO). |
|
Exp Occ |
Expediting Occurrence: The ID of an expedite item within a list of expedite items related to a PO position. |
|
Suppl Occ |
Supplementary Occurrence: The ID of a supplementary occurrence of an expedite item in a PO. |
|
Material Id |
The ID of a material related to a PO. |
|
Description |
The description of a material related to a PO position. |
|
Exp Qty |
The quantity of an expedite item in a PO related to an inspection visit. |
|
Deliverable Flag |
Indicates an expediting item is deliverable. |
|
IRC |
Release Certificate: The ID of a release number for an inspection visit. |
|
NRC |
Non-Release Certificate: The ID of a certificate with details of the items that did not pass inspection. |
|
Visit Pack |
The ID of a group of expedite items for an inspection release. |
|
Barcode |
The barcode related to an inspection visit. |
The following table describes the fields in the Schedule Milestones tab.
|
Field |
Description |
|---|---|
|
Seq |
The unique sequence of a milestone related to a schedule. The sequence is calculated as per the order in which the milestones are expected to occur in a schedule. |
|
Description |
The description of a milestone or a lead time related to a schedule. |
|
Baseline |
The planned date of a milestone related to a schedule. |
|
Duration before baseline |
The number of days between one milestone to the next milestone. |
|
Milestone Duration |
The number of days required to complete a milestone. |
|
Forecast Start |
The date when a milestone of a schedule is scheduled to start. |
|
Forecast Complete |
The date when a milestone of a schedule is scheduled to complete. |
|
Actual |
The date when a milestone of a schedule is achieved. |
|
Deadline Float |
The total time by when you can delay a schedule milestone without delaying the deadline. |
|
Calendar |
The calendar related to a milestone of a schedule. |
The following table describes the fields in the Attachments tab.
|
Field |
Description |
|---|---|
|
R |
Restriction: The restriction status of a URL according to the rules maintained in the s00040 Hyperlink Restrictions screen. The R field is applicable only for hyperlink attachments. |
|
Link or File |
Indicates whether an attachment is a file or a hyperlink. |
|
Attachment Type |
The type of an attachment. The valid attachment types are defined in the s00072 Attachment Type screen. The Attachment Type field helps in grouping and categorization of the attachments. |
|
Rev Stat |
Revision Status: Indicates the status of a revision. There are three statuses:
|
|
Revision |
The revision number of an attachment. When you create a new revision, the revision number increases by one. |
|
Link Ver |
Link Version: Indicates the version number of the owning entity, such as POs and TMRs. |
|
Id/ Filename |
The ID of a hyperlink or the name of a file attachment. |
|
Title/Description |
The title of a hyperlink or the description of a file attachment. |
|
Stat |
Status: Indicates the status of an attachment. If the Stat checkbox is selected, the attachment is active. |
|
Ext Visible |
Externally Visible: Indicates an attachment is visible in external systems, such as the Supplier Portal. |
|
Links |
Indicates whether an attachment is linked to or from another entity, such as a PO or a TMR. |
|
Url |
The URL of a hyperlink attachment. |