Update the status of a schedule

  • Last UpdatedMay 07, 2026
  • 1 minute read

Change the status of a schedule based on your requirements.

  1. Navigate to the s52002 Inspection / Expedite Schedule screen.

  2. In the Current Project control block, from the Project dropdown, select the required project ID.

  3. To refresh the screen, select the F5 key.

  4. In the Inspection Schedules grid, select a row.

  5. On the s52002 menu, in the Options group, from Workflow dropdown, select one of the following:

    • Close Schedule: The schedule is closed and you cannot update the schedule.

    • Change Schedule: You can update the baseline and forecast dates of the schedule.

    • Finish Schedule: The schedule is completed and you cannot update the schedule. The purchase order related to the schedule is completed and ready to close out.

  6. (Optional) To revert the status update, on the s52002 menu, in the Options group, from Workflow dropdown, select Reset status change.

  7. To save the changes, on the Home menu, in the Record group, select Save.