View the inspection progress of a schedule

  • Last UpdatedMay 07, 2026
  • 1 minute read

View the inspection progress of the expedite items in a Purchase Order (PO) related to a schedule. View the inspection progress details such as total items released, items not released, released percentage, and so on.

  1. Navigate to the s52002 Inspection / Expedite Schedule screen.

  2. In the Current Project control block, from the Project dropdown, select the required project ID.

  3. To refresh the screen, select the F5 key.

  4. In the Inspection Schedules grid, select a row.

  5. Select the Inspection Progress tab and view the inspection progress of the PO.

    For more information on all the fields, see s52002 Field descriptions.