AVEVA Enterprise Resource Management

s50039 Field descriptions

  • Last UpdatedMay 07, 2026
  • 8 minute read

Common fields in the screen

Field

Description

SI

Status Indicator: Indicates the status of a record related to validation errors, warnings, and updates.

Defined By

The ID of a user who created a record.

Defined At

The date and time when a record was created.

Updated By

The ID of a user who updated a record.

Updated At

The date and time when a record was updated.

Type

Defines the relationship between a procurement schedule and the materials related to the procurement schedule. The schedule types are defined in the s50031 Schedule Types screen. There are four types:

  • COMP: The procurement schedule is related to a project component. The COMP type schedule can contain both project related and corporate defined milestones.

  • M: The manual procurement schedule created outside AVEVA Enterprise Resource Management.

  • MR: The procurement schedule is related to an Material Requisition (MR).

  • TMR: The procurement schedule is related to a Technical Material Requisition (TMR).

Project control block

Field

Description

Project

The ID of a project.

Include Finished Schedule

Indicates the finished procurement schedules appear in the Procurement Schedules grid.

Required on Site Between

The dates between which an item in a procurement schedule is required on site.

Milestone late lookahead days

The number of days the next milestone is late for a procurement schedule.

If the value in the Milestone late lookahead days field is 0, the Milestone Late action loads procurement schedules that are already late for the next milestone. However, if the value in the Milestone late lookahead days field is more than 0, the Milestone Late action loads procurement schedules for which the next milestone is late for the number of days as defined in the Milestone late lookahead days field. For example, if the value in the Milestone late lookahead days field is 5, then the Milestone Late action loads procurement schedules for which the next milestone is late for five days.

Procurement Schedules grid

The following table describes the fields in the General tab.

Field

Description

A

Alarm: Indicates a procurement schedule is critical towards the delivery deadline (the Required on Site At date).

AC

Activity Critical: Indicates a procurement schedule is activity critical, that is, the schedule affects the start date of a particular activity.

MC

Milestone Critical: Indicates a procurement schedule is milestone critical, that is, the schedule affects the forecast date of the next milestone.

Id

The ID of a procurement schedule.

Title

The title of a procurement schedule.

Status

The status of a procurement schedule. The different statuses are:

  • Open: The planning stage where the milestones and dates are updated. A procurement schedule is created in the Open status.

  • Closed: The locked status where you can only update the actual dates and reschedule the forecasts. You cannot update the status of a procurement schedule from Closed to Open. The actual date of a procurement schedule will automatically update once the status is changed from Open or Finished to Closed.

  • Change: The stage where a procurement schedule is open for modification of the schedule, dates, milestones, and so on. The actual date of a procurement schedule will automatically update once the status is changed from Open or Finished to Change.

  • Finished: The terminal or intermediate state for completed procurement schedule or procurement schedules not in use. You can update the status of a procurement schedule from Finished to Change.

MR/TMR

Material Requisition/ Technical Material Requisition: The MR or the TMR for which a procurement schedule is created.

MR Rev

Material Requisition Revision: The revision of a TMR. The TMR revision is defined for an MR in the s50016 Technical Material Requisition screen or for the MR transfer in the s40001 Requisition Register screen.

Project Component

The project component for which a procurement schedule is created.

Forecast Calc At

Forecast Calculated At: The date when the last schedule forecast was calculated.

Required on Site at

The date when an item in a procurement schedule is required on site.

Forecast

The expected delivery date of the ordered item at the location agreed upon in the delivery terms of the Purchase Order (PO) related to a procurement schedule.

ROS Float

Required On Site Float: The amount of time the Forecast may be delayed and still arrive prior to the Required on Site at date.

ROS-Activity

Required On Site Activity: The activity that is estimated to have the earliest need of the item targeted by a procurement schedule.

Activity Start

The start date of an activity that is estimated to have the earliest need of the item targeted by a procurement schedule.

Float on Act Start

Float on Activity Start: The amount of days the Forecast may be delayed without delaying the Activity Start date of a linked activity.

Next Milestone

The milestone that is next in sequence with an actual date, after the current milestone.

Next Forecast Date

The expected date when the next milestone is completed.

Multiple POs

Multiple Purchase Orders: Indicates that multiple POs are related to a procurement schedule.

PO No

Purchase Order Number: If only one PO is relevant for a procurement schedule, the PO No field displays the relevant PO number. If Multiple POs checkbox is selected, the POs are listed in the Purchase Orders tab.

Buyer

If only one PO is relevant for a procurement schedule, the Buyer field displays the buyer of the PO. If Multiple POs checkbox is selected, the POs are listed in the Purchase Orders tab.

Expediter

If only one PO is relevant for a procurement schedule, the Expeditor field displays the expediter of the PO. If Multiple POs checkbox is selected, the POs are listed in the Purchase Orders tab.

Schedule Details grid

In the Schedule Milestones tab, in the Procurement Schedule Milestones grid, the following table describes the fields in the General tab.

Field

Description

FC

Forecast Critical: Indicates the milestone forecast of a procurement schedule is time critical. There are three statuses:

  • Red: The milestone forecast is after the baseline.

  • Yellow: The milestone forecast is up to two days earlier or on the baseline.

  • Green: The milestone forecast is before the baseline by three or more days.

    The status is empty for lead time lines and milestones with no baseline.

Calculation Sequence

The sequence in which the milestones are scheduled. If the default sequence number of a line item defined in the s50033 Procurement Milestones screen already exists in Calculation Sequence field, the sequence of either line items is required to be changed to save the milestone.

Schedule Item Type

The type of a schedule item. The valid values are as follows:

  • M (Procurement Milestone): Display all active milestones defined as Corporate or Project in the s50033 Procurement Milestones screen in the Id dropdown.

  • LT (Procurement Lead Time): Display all active lead times defined as Corporate or Project in the s50033 Procurement Milestones screen in the Id dropdown.

    The procurement milestones or lead times are defined in the s50033 Procurement Milestones screen. The schedule item type IDs and descriptions are defined in the s50032 Schedule Item Types screen.

Id

The ID of a milestone or a lead time. The IDs are defined in the s50033 Procurement Milestones screen

Baseline

The planned duration used to create the baseline of a procurement milestone.

Forecast

The expected delivery date for a milestone in a procurement schedule. The forecast is applicable only if the procurement Schedule Item Type is M (Procurement Milestone).

Actual Date

The date when a procurement milestone is achieved. The actual date is applicable only if the procurement Schedule Item Type is M (Procurement Milestone).

Float

The difference between the Baseline and the Forecast dates of a procurement milestone.

The following table describes the fields in the Journal tab.

Field

Description

Note

The comments related to the status of a procurement schedule.

The following table describes the fields in the TMRs tab.

Field

Description

TMR

Technical Material Requisition: The ID of a TMR or a MR related to a procurement schedule.

Title

The title of a requisition related to a schedule.

Status

The internal status of a TMR. The value is defined in the s50016 Technical Material Requisition screen. For an MR, if no TMR is generated from the MR, the Status field is empty.

Ver

Version: The version number of a TMR. The value is defined in the s50016 Technical Material Requisition screen. For an MR, if no TMR is generated from the MR, the Version field is empty.

MR Rev

Material Requisition Revision: The latest revision number of a TMR generated from an MR. The value is defined in the s50016 Technical Material Requisition screen and s40001 Requisition Register screen. For an MR, if no TMR is generated from the MR, the MR Rev field is empty.

Issued

The date when a TMR is issued. The value is defined in the s50016 Technical Material Requisition screen. For an MR, if no TMR is generated from the MR, the Issued field is empty.

Required on Site at

The date when an item in a TMR is required on site. For an MR, if no TMR is generated from the MR, the Required on Site at field is empty.

Issue Purpose

The purpose of issuing a TMR. For an MR, if no TMR is generated from the MR, the Issue Purpose field is empty.

Responsible

The ID of a user responsible for a TMR. If the schedule is related to an MR, then the responsible user is the owner of the requisition in the s40001 Requisition Register screen, and if the schedule is TMR based, then the responsible user is the technical handler of the TMR in the s50016 Technical Material Requisition screen.

In the Component tab, in the Component grid, the following table describes the fields in the General tab.

Field

Description

Comp Id

Component ID: The ID of a project component related to a procurement schedule.

Description

The description of a project component related to a procurement schedule.

Status

The internal status of a project component related to a procurement schedule. The valid value is defined in the s20010 Project Components screen.

Responsible

The ID of a user responsible for the project component related to a procurement schedule.

Activity

The activity related to the project component. The valid value is defined in the s20010 Project Components screen.

Correctional Time

The number of days before or after the activity start date at which the project component is required in production. The valid value is defined in the s20010 Project Components screen.

Project Component Requirement Date

The date when the project component related to a procurement schedule is required on site. The valid value is defined in the s20010 Project Components screen.

Quantity

The quantity of a project component related to a procurement schedule.

Unit

The unit of measure for a project component.

The following table describes the fields in the Purchase Orders tab.

Field

Description

PO No

Purchase Order Number: The PO number of the PO related to a procurement schedule.

Po Code

Purchase Order Code: The purchase code ID of the PO related to a procurement schedule.

Title

The title of a PO related to a procurement schedule.

Buyer

The buyer of a PO related to a procurement schedule.

Status

The internal status of a PO related to a procurement schedule. The valid value is defined in the s50018 Purchase Order screen.

Ver

Version: The version number of a PO related to a procurement schedule.

Issued Date

The date when a PO is issued for the first time. Subsequent changes to PO do not impact the Issued Date.

Issued By

The ID of a user who issued a PO for the first time.

Forecast Del Date

Forecast Delivery Date: The expected delivery date of the ordered item at the location agreed upon in the delivery terms of the PO related to a procurement schedule.

Delivery Status

Indicates the purchased item is delivered for the PO related to a procurement schedule.

Expediter

The ID of an expediter for a PO related to a procurement schedule.

Supplier

The ID of a supplier related to a PO. The valid value is defined in the s50018 Purchase Order screen.