s50039 Field descriptions
- Last UpdatedMay 07, 2026
- 8 minute read
Common fields in the screen
|
Field |
Description |
|---|---|
|
SI |
Status Indicator: Indicates the status of a record related to validation errors, warnings, and updates. |
|
Defined By |
The ID of a user who created a record. |
|
Defined At |
The date and time when a record was created. |
|
Updated By |
The ID of a user who updated a record. |
|
Updated At |
The date and time when a record was updated. |
|
Type |
Defines the relationship between a procurement schedule and the materials related to the procurement schedule. The schedule types are defined in the s50031 Schedule Types screen. There are four types:
|
Project control block
|
Field |
Description |
|---|---|
|
Project |
The ID of a project. |
|
Include Finished Schedule |
Indicates the finished procurement schedules appear in the Procurement Schedules grid. |
|
Required on Site Between |
The dates between which an item in a procurement schedule is required on site. |
|
Milestone late lookahead days |
The number of days the next milestone is late for a procurement schedule. If the value in the Milestone late lookahead days field is 0, the Milestone Late action loads procurement schedules that are already late for the next milestone. However, if the value in the Milestone late lookahead days field is more than 0, the Milestone Late action loads procurement schedules for which the next milestone is late for the number of days as defined in the Milestone late lookahead days field. For example, if the value in the Milestone late lookahead days field is 5, then the Milestone Late action loads procurement schedules for which the next milestone is late for five days. |
Procurement Schedules grid
The following table describes the fields in the General tab.
|
Field |
Description |
|---|---|
|
A |
Alarm: Indicates a procurement schedule is critical towards the delivery deadline (the Required on Site At date). |
|
AC |
Activity Critical: Indicates a procurement schedule is activity critical, that is, the schedule affects the start date of a particular activity. |
|
MC |
Milestone Critical: Indicates a procurement schedule is milestone critical, that is, the schedule affects the forecast date of the next milestone. |
|
Id |
The ID of a procurement schedule. |
|
Title |
The title of a procurement schedule. |
|
Status |
The status of a procurement schedule. The different statuses are:
|
|
MR/TMR |
Material Requisition/ Technical Material Requisition: The MR or the TMR for which a procurement schedule is created. |
|
MR Rev |
Material Requisition Revision: The revision of a TMR. The TMR revision is defined for an MR in the s50016 Technical Material Requisition screen or for the MR transfer in the s40001 Requisition Register screen. |
|
Project Component |
The project component for which a procurement schedule is created. |
|
Forecast Calc At |
Forecast Calculated At: The date when the last schedule forecast was calculated. |
|
Required on Site at |
The date when an item in a procurement schedule is required on site. |
|
Forecast |
The expected delivery date of the ordered item at the location agreed upon in the delivery terms of the Purchase Order (PO) related to a procurement schedule. |
|
ROS Float |
Required On Site Float: The amount of time the Forecast may be delayed and still arrive prior to the Required on Site at date. |
|
ROS-Activity |
Required On Site Activity: The activity that is estimated to have the earliest need of the item targeted by a procurement schedule. |
|
Activity Start |
The start date of an activity that is estimated to have the earliest need of the item targeted by a procurement schedule. |
|
Float on Act Start |
Float on Activity Start: The amount of days the Forecast may be delayed without delaying the Activity Start date of a linked activity. |
|
Next Milestone |
The milestone that is next in sequence with an actual date, after the current milestone. |
|
Next Forecast Date |
The expected date when the next milestone is completed. |
|
Multiple POs |
Multiple Purchase Orders: Indicates that multiple POs are related to a procurement schedule. |
|
PO No |
Purchase Order Number: If only one PO is relevant for a procurement schedule, the PO No field displays the relevant PO number. If Multiple POs checkbox is selected, the POs are listed in the Purchase Orders tab. |
|
Buyer |
If only one PO is relevant for a procurement schedule, the Buyer field displays the buyer of the PO. If Multiple POs checkbox is selected, the POs are listed in the Purchase Orders tab. |
|
Expediter |
If only one PO is relevant for a procurement schedule, the Expeditor field displays the expediter of the PO. If Multiple POs checkbox is selected, the POs are listed in the Purchase Orders tab. |
Schedule Details grid
In the Schedule Milestones tab, in the Procurement Schedule Milestones grid, the following table describes the fields in the General tab.
|
Field |
Description |
|---|---|
|
FC |
Forecast Critical: Indicates the milestone forecast of a procurement schedule is time critical. There are three statuses:
|
|
Calculation Sequence |
The sequence in which the milestones are scheduled. If the default sequence number of a line item defined in the s50033 Procurement Milestones screen already exists in Calculation Sequence field, the sequence of either line items is required to be changed to save the milestone. |
|
Schedule Item Type |
The type of a schedule item. The valid values are as follows:
|
|
Id |
The ID of a milestone or a lead time. The IDs are defined in the s50033 Procurement Milestones screen |
|
Baseline |
The planned duration used to create the baseline of a procurement milestone. |
|
Forecast |
The expected delivery date for a milestone in a procurement schedule. The forecast is applicable only if the procurement Schedule Item Type is M (Procurement Milestone). |
|
Actual Date |
The date when a procurement milestone is achieved. The actual date is applicable only if the procurement Schedule Item Type is M (Procurement Milestone). |
|
Float |
The difference between the Baseline and the Forecast dates of a procurement milestone. |
The following table describes the fields in the Journal tab.
|
Field |
Description |
|---|---|
|
Note |
The comments related to the status of a procurement schedule. |
The following table describes the fields in the TMRs tab.
|
Field |
Description |
|---|---|
|
TMR |
Technical Material Requisition: The ID of a TMR or a MR related to a procurement schedule. |
|
Title |
The title of a requisition related to a schedule. |
|
Status |
The internal status of a TMR. The value is defined in the s50016 Technical Material Requisition screen. For an MR, if no TMR is generated from the MR, the Status field is empty. |
|
Ver |
Version: The version number of a TMR. The value is defined in the s50016 Technical Material Requisition screen. For an MR, if no TMR is generated from the MR, the Version field is empty. |
|
MR Rev |
Material Requisition Revision: The latest revision number of a TMR generated from an MR. The value is defined in the s50016 Technical Material Requisition screen and s40001 Requisition Register screen. For an MR, if no TMR is generated from the MR, the MR Rev field is empty. |
|
Issued |
The date when a TMR is issued. The value is defined in the s50016 Technical Material Requisition screen. For an MR, if no TMR is generated from the MR, the Issued field is empty. |
|
Required on Site at |
The date when an item in a TMR is required on site. For an MR, if no TMR is generated from the MR, the Required on Site at field is empty. |
|
Issue Purpose |
The purpose of issuing a TMR. For an MR, if no TMR is generated from the MR, the Issue Purpose field is empty. |
|
Responsible |
The ID of a user responsible for a TMR. If the schedule is related to an MR, then the responsible user is the owner of the requisition in the s40001 Requisition Register screen, and if the schedule is TMR based, then the responsible user is the technical handler of the TMR in the s50016 Technical Material Requisition screen. |
In the Component tab, in the Component grid, the following table describes the fields in the General tab.
|
Field |
Description |
|---|---|
|
Comp Id |
Component ID: The ID of a project component related to a procurement schedule. |
|
Description |
The description of a project component related to a procurement schedule. |
|
Status |
The internal status of a project component related to a procurement schedule. The valid value is defined in the s20010 Project Components screen. |
|
Responsible |
The ID of a user responsible for the project component related to a procurement schedule. |
|
Activity |
The activity related to the project component. The valid value is defined in the s20010 Project Components screen. |
|
Correctional Time |
The number of days before or after the activity start date at which the project component is required in production. The valid value is defined in the s20010 Project Components screen. |
|
Project Component Requirement Date |
The date when the project component related to a procurement schedule is required on site. The valid value is defined in the s20010 Project Components screen. |
|
Quantity |
The quantity of a project component related to a procurement schedule. |
|
Unit |
The unit of measure for a project component. |
The following table describes the fields in the Purchase Orders tab.
|
Field |
Description |
|---|---|
|
PO No |
Purchase Order Number: The PO number of the PO related to a procurement schedule. |
|
Po Code |
Purchase Order Code: The purchase code ID of the PO related to a procurement schedule. |
|
Title |
The title of a PO related to a procurement schedule. |
|
Buyer |
The buyer of a PO related to a procurement schedule. |
|
Status |
The internal status of a PO related to a procurement schedule. The valid value is defined in the s50018 Purchase Order screen. |
|
Ver |
Version: The version number of a PO related to a procurement schedule. |
|
Issued Date |
The date when a PO is issued for the first time. Subsequent changes to PO do not impact the Issued Date. |
|
Issued By |
The ID of a user who issued a PO for the first time. |
|
Forecast Del Date |
Forecast Delivery Date: The expected delivery date of the ordered item at the location agreed upon in the delivery terms of the PO related to a procurement schedule. |
|
Delivery Status |
Indicates the purchased item is delivered for the PO related to a procurement schedule. |
|
Expediter |
The ID of an expediter for a PO related to a procurement schedule. |
|
Supplier |
The ID of a supplier related to a PO. The valid value is defined in the s50018 Purchase Order screen. |