AVEVA Enterprise Resource Management

s50022 Field descriptions

  • Last UpdatedFeb 11, 2025
  • 7 minute read

Purchasing View Tab

In the Material grid, the following table describes the fields in the Material tab.

Field

Description

SI

Status Indicator: Indicates the status of the record related to validation errors, warnings, and updates.

S

Status: Indicates the amount in purchase order compared to the requirements. There are three statuses:

  • Red: The purchased quantity is less than needed.

  • Yellow: The purchased quantity is higher than needed.

  • Green: The purchased quantity is equal to the need.

TMR Quantity

The total Technical Material Requisition (TMR) quantity requested for transfer to a TMR.

A

Alarm: Indicates the status for a material is critical. The alarm is on if the the requirements are higher than the available material holding.

LC

Location Critical: Indicates the stock holding for a material in one or more sites are critical.

On PA

On Purchase Agreement: Identifies the Purchase Agreement related to a material.

Project

The ID of a project related to a material.

MC

Material Code: Indicates the material code of a material.

Item Id

The ID of a material in a TMR position. MC field input is required for list-of-values of item ID to be available.

Main Item Id

The ID of a project component or fabricate which has been broken down into supplementary items.

SMC

Standard Material Category: Indicates whether a material is controlled as a standard stock material or a project related material. The valid categories are defined and maintained in the s20011 Standard Materials screen.

Description

The description of a material.

Class

The material classification code of a material.

Buyer Group

The group of purchasers responsible for procuring a requisitioned item.

Mat Type

Material Type: The grouping of a material, for example pipe, cables, and so on.

Dimension

The dimension of a material.

Type description

The description of the Material Type.

Supplier

The ID of the preferred supplier for a requisitioned material. The field value is blank for materials that have SMC value as P.

Site Id

The unique ID of the site where the requisitioned items are procured. The site ID related to the information in LT and PO Date fields.

LT

Lead Time: The time taken to receive materials from a supplier after an order is placed.

PO Date

The purchase date for a material. The purchase date is calculated as critical date minus lead time.

Date

The first critical date for material requirements across all sites.

Open PO

Indicates the material exists in a purchase order in status Create/Changed or Approval.

Exists TMR

Indicates the material exists in a TMR position which is not related to a purchase order.

In the Site grid, the following table describes the fields in the General tab.

Field

Description

A

Alarm: Indicates the status for a material is critical. The alarm is on if the the requirements are higher than the available material holding.

Site Id

The unique ID of the site where the requisitioned items are procured.

Balance

The quantity of remaining material for each site in comparison to the material requirements. The balance is calculated as negative quantities from requirements and positive quantities from closed purchase orders.

Not Requisition qty

The sum of the material quantity with FR checkbox as cleared in the Material Balance tab.

Supplier

The ID of the preferred supplier for a requisitioned material.

Supplier Name

The company name of a supplier.

SMC

Standard Material Category: Indicates whether a material is controlled as a standard stock material or a project related material. The valid categories are defined and maintained in the s20011 Standard Materials screen.

Buyer Group

The group of purchasers responsible for procuring a requisitioned item.

ROP

Reorder Point: The standard material stock level when the material is reordered. The ROP for a standard material is defined in the s20011 Standard Materials screen.

ROQ

Reorder Quantity: The quantity of standard material to be reordered at the ROP. The ROQ for a standard material defined in the s20011 Standard Materials screen.

LT

Lead Time: The time taken to receive materials from a supplier after an order is placed.

PO Date

The purchase date for a material. The purchase date is calculated as critical date minus lead time.

Date

The first critical date for material requirements across all sites.

In the Material Balance grid, the following table describes the fields in the Material Balance tab.

Field

Description

MS-code

Material Status Code: The material transaction code of the material to determine the nature of the material transaction. For example, the MS-code is TMR for the expected material from a TMR with Closed status. The MS-code is defined in the s50008 Material Status Code screen.

Site

The unique ID of the site where the requisitioned items are procured.

Transaction Id

The code to identify a material transaction.

System

The ID of the system related to a material.

FR

For Requisition: Indicates a material exists as a requisition in a part list, a Delivery Request List (DRL), or a picking list.

Activity

The ID of the activity related to a material.

Cor

Activity Correction Time: The correction time related to the start date of an activity.

Date

The date a material is expected to become available.

Quantity

The quantity of the material requirement at a particular site.

BBQ

Buyer's Balance Quantity: The quantity of material that contributes to the material balance.

Balance

The quantity of remaining material for each transaction in comparison to the material requirements.

TMR Quantity

The TMR quantity requested for transfer to a TMR.

Requisitioning View Tab

The following table describes the fields in the Search Planned Requisitions Control Block.

Field

Description

Project

The ID of a project related to a Material Requisitions (MR).

MR Number

Material Requisition Number: The ID of the MR for which related materials are searched. The MR numbers are defined in the s40001 Requisition Register screen.

All

Indicates to display all over-requisitioned and under-requisitioned materials. If the All checkbox is selected, the Req Status difference dropdown is not available.

Req Status difference

Indicates the material requisition type that is searched. There are three types:

  • All Non-Matching Quantities: All under-requisitioned and over-requisitioned materials (which exceed the rounding increment setting defined in the s40002 Working Surplus Contingency screen) are searched.

  • Requirement above TMR Quantity: All under-requisitioned materials are searched.

  • TMR Quantity above Requirement: All over-requisitioned materials are searched.

    The Req Status difference dropdown is available only if the All checkbox is cleared and an MR Number is selected.

In the Materials grid, the following table describes the fields in the General tab.

Field

Description

RS

Requisition Status: Indicates the requisition status of a material. There are three statuses:

  • Red: The requisitioned quantity is less than required.

  • Yellow: The requisitioned quantity is higher than required.

  • Green: The requisitioned quantity is equal to the required.

Project

The ID of a project related to a material.

Site

The unique ID of the site where the requisitioned items are procured.

MC

The material code for a material.

Item Id

The code to identify a material in a TMR position.

Description

The description of a material.

Group/Split Col 1-5

The grouping of requisitioned materials by up to five attributes. The grouping attributes are defined in the d0228 MR Filter Builder dialog from the s40001 Requisition Register screen.

Dimension

The dimension of a material.

TMR Balance

The material balance between the required quantity and the requisitioned quantity.

Unit

The unit of measurement of a material quantity.

TMR Qty

The TMR quantity requested for transfer to a TMR.

Total Rqmt

The required material quantity that includes working surplus and contingency quantity.

PC Qty

The required material quantity from the estimated quantity (Est Qty) field in the s20010 Project Components screen.

On Hold Qty

The engineering on hold material quantity from a Material Take-Off (MTO) or a Part List.

Adjustment

The adjustment to be made to a Total Take-Off quantity.

Adj %-age

The percentage of the adjustment to be made to a Total Take-Off quantity.

MTO Qty

The required material quantity that excludes working surplus and contingency quantity.

Wrk Surplus

The working surplus quantity to be requisitioned with an MTO quantity. The working surplus quantity covers additional material requirement due to wastage. The rules to calculate working surplus quantity are defined in the s40002 Working Surplus Contingency screen.

Contingency

The contingency quantity to be requisitioned with an MTO quantity. The contingency quantity covers additional material requirements due to any inaccuracies in the requirement quantity. The rules to calculate contingency quantity are defined in the s40002 Working Surplus Contingency screen.

Rounding Qty

The rounded required material quantity. The rules to calculate rounding are defined in the s40002 Working Surplus Contingency screen.

Estimated Qty

The total material requirement from an Advance Bill of Material or the estimated material requirements for project components from a project component catalogue.

SMC

Standard Material Category: Indicates whether a material is controlled as a standard stock material or a project related material. The valid categories are defined and maintained in the s20011 Standard Materials screen.

Class

The material classification code of a material.

Buyer Group

The group of purchasers responsible for procuring a requisitioned item.

Mat Type

Material Type: The grouping of a material, for example pipe, cables, and so on.

Type

The type of a material or a component defined in their respective catalogues.

Supplier

The ID of the preferred supplier for a requisitioned standard material. The supplier ID is defined in the s20011 Standard Materials screen.

In the Material Balance grid, the following table describes the fields in the Material Balance tab.

Field

Description

MS-code

Material Status Code: The material transaction code of the material to determine the nature of the material transaction. For example, the MS-code is TMR for the expected material from a TMR with Closed status. The MS-code is defined in the s50008 Material Status Code screen.

Site

The unique ID of the site where the requisitioned items are procured.

Transaction Id

The code to identify a material transaction.

System

The ID of the system related to a material transaction.

Activity

The ID of the activity related to a material.

Cor

Activity Correction Time: The correction time related to the start date of an activity.

Date

The date when the material is expected to become available.

On Hold Qty

The engineering on hold material quantity from a Material Take-Off (MTO) or a part list.

Quantity

The quantity of the material requirement at a particular site.

Unit

The unit of measurement of a material.