Please ensure Javascript is enabled for purposes of website accessibility
Powered by Zoomin Software. For more details please contactZoomin

AVEVA Enterprise Resource Management

Create a split value for a system budget

  • Last UpdatedMay 07, 2026
  • 1 minute read

Use a budget split to identify a heavy cost bearer. When you save the split values, the system updates the original estimate value for each cost type.

  1. Navigate to the s10007 Project System Budget screen.

  2. In the Current Project control block, from the Project dropdown, select the ID of the required project.

  3. To refresh the screen, select the F5 key.

  4. In the Levels and Systems grid, select a row.

  5. In the Systems grid, select a row.

  6. In the Related Data grid, select one of the following:

    • Org Est Split: To create an original estimate split.

    • Budget Split: To create a budget split.

    • F.cast split: To create a forecast split.

    Note: In the selected tab, ensure no records exist.

  7. On the s10007 menu, in the Copy/Import Split values group, select Create Split Values.

    In the grid, a blank row is created.

  8. In the grid, in the Record No field, enter the unique ID of a split.

  9. (Optional) Enter the relevant details in other fields as required. For more information on all the fields, see s10006 Field descriptions.

  10. On the Home menu, in the Record group, select Save.

    The split is created.

TitleResults for “How to create a CRG?”Also Available in