Update the baseline date of a schedule

  • Last UpdatedMay 07, 2026
  • 1 minute read

The baseline date is the agreed date for the completion of the activities related to a schedule. Before you update the baseline date, ensure the status of the schedule is Open or Change.

  1. Navigate to the s52002 Inspection / Expedite Schedule screen.

  2. In the Current Project control block, from the Project dropdown, select the required project ID.

  3. To refresh the screen, select the F5 key.

  4. In the Inspection Schedules grid, select a row.

  5. On the s52002 menu, in the Scheduling group, select Update Baseline.

    In the Inspection Schedules grid, in the General tab, the date in the Forecast field is copied to the Baseline field.

  6. To save the changes, on the Home menu, in the Record group, select Save.