AVEVA Enterprise Resource Management

s40001 Field descriptions

  • Last UpdatedMay 07, 2026
  • 4 minute read

Common fields in the screen

Field

Description

SI

Status Indicator: Indicates the status of a record related to validation errors, warnings, and updates.

Defined By

The ID of a user who created a record.

Defined At

The date and time when a record was created.

Updated By

The ID of a user who updated a record.

Updated At

The date and time when a record was updated.

Current Project control block

Field

Description

Project

The ID of a project related to an MR.

Description

The description of a project related to an MR.

Status

Indicates the status of a project. If the Status checkbox is selected, the project is available for use throughout AVEVA Enterprise Resource Management.

Template

Indicates a project is a template project. A template project is a standard project that can help set up projects with the same method and structure as the template project. If the Template checkbox is selected, the project is not included in material status calculations or budget calculations.

MR Numbers grid

The following table describes the fields in the General tab.

Field

Description

MR Number

Material Requisition (MR) Number: The unique ID of an MR.

Priority

The number to determine the priority of an MR for a project.

Title

The title of an MR.

Requisition Category

The ID of a requisition category related to an MR.

Status

Indicates the status of an MR. If the Status checkbox is selected, the MR is available for use throughout AVEVA Enterprise Resource Management.

Site Id

The ID of a site related to an MR.

Discipline

The ID of a drawing discipline related to an MR.

System

The ID of a system related to an MR.

Owner

The ID of a user who is the owner of an MR.

VDRS

Vendor Deliverable Requirements Schedule (VDRS): Indicates an MR requires a VDRS.

Proc Sch Required

Procurement Schedule Required: Indicates an MR requires a procurement schedule.

End Date

The end date of an MR.

Current Revision

The latest revision number of the TMR generated for an MR.

Current Version

The latest version number of the TMR generated for an MR.

Creation Method

The method used to create the TMR for an MR.

Created to top up

The number of the MR that was created to top up the current MR.

External TMR Status

The external status of the TMR generated for an MR.

Internal TMR Status

The internal status of the TMR generated for an MR.

Rejected

Indicates the TMR is rejected in approval.

Comment

The comments related to a TMR.

Issue Purpose

The purpose for issuing a TMR.

Issue Date

The date when the current revision of an MR was issued.

Previously Issued Revision

The date when the previous version of an MR was issued.

Summary

The material summary linked to an MR.

Version assigned to TMR

The version number of a material summary for which the current TMR is created or updated.

Current Version

The current version of a material summary related to an MR.

The following table describes the fields in the MR Filter tab.

Field

Description

MR Filter

The textual representation of the filter defined for an MR in the d0228 MR Filter Builder dialog.

Procurement Scheduling grid

Field

Description

A

Alarm: Indicates a procurement schedule is critical towards the delivery deadline (the Required on Site At date).

AC

Activity Critical: Indicates a procurement schedule is activity critical, that is, the schedule affects the start date of a particular activity.

MC

Milestone Critical: Indicates a procurement schedule is milestone critical, that is, the schedule affects the forecast date of the next milestone.

SC

Schedule Changed: Indicates a procurement schedule has been updated since the last time forecasts were calculated. You can track the SC field to ensure that the most current and accurate information is considered for procurement decisions and forecasting future project timeline.

Id

The unique ID of a procurement schedule.

Title

The title of a procurement schedule.

Required on Site at

Required on Site at (RoS): The date when a material is required on site.

Forecast

The expected delivery date of a material in procurement schedule, if the deadlines in the procurement schedule are met.

ROS Float

The amount of time the value in the Forecast field may be delayed and still arrive prior to the date in the Required on Site field.

Activity

The ID of an activity related to a procurement schedule.

Activity Start

The start date of an activity that is estimated to have the earliest need of the material targeted by a procurement schedule.

Float on Act Start

Float on Activity Start: The amount of days the value in the Forecast field may be delayed without delaying the date in the Activity Start Date field of a linked activity.

Schedule Milestones grid

Field

Description

FC

Forecast Critical: Indicates the milestone forecast of a procurement schedule is time critical. There are three statuses:

  • Red: The milestone forecast is after the baseline.

  • Yellow: The milestone forecast is up to two days earlier or on the baseline.

  • Green: The milestone forecast is before the baseline by three or more days.

    The status is empty for lead time lines and milestones with no baseline.

Calc Seq

Calculation Sequence: The unique sequence in which the milestones are scheduled.

Type

Indicates whether an item in a procurement schedule is a milestone or a lead time.

Id

The ID of a milestone or a lead time.

Baseline

The planned date for a procurement milestone.

Forecast

The expected delivery date for a milestone in a procurement schedule.

Actual Date

The date when a procurement milestone is achieved.

Float

The difference between the values in the B and F fields of a procurement milestone.