View unscheduled TMRs

  • Last UpdatedMay 07, 2026
  • 1 minute read

View the unscheduled Technical Material Requisitions (TMRs) for a project. In the s50016 Technical Material Requisition screen, view the TMRs that fulfill the following conditions:

  • The TMR is defined for the selected project.

  • In the s50016 Technical Material Requisition screen, in the Technical Material Requisition Header grid, in the General tab, the following exists:

    • The Proc Sch Required checkbox is selected.

    • The value in the MR Revision field is not defined.

  • The TMR is not registered on a procurement schedule.

To view unscheduled TMRs

  1. Navigate to the s50039 Procurement Status screen.

  2. In the Project control block, from the Project dropdown, select the ID of the required project.

  3. On the s50039 menu, in the Show Unscheduled group, select TMRs.

    The s50016 Technical Material Requisition screen appears.

    In the Technical Material Requisition Header grid, a list of unscheduled TMRs for the selected project appears.