View unscheduled TMRs
- Last UpdatedMay 07, 2026
- 1 minute read
View the unscheduled Technical Material Requisitions (TMRs) for a project. In the s50016 Technical Material Requisition screen, view the TMRs that fulfill the following conditions:
-
The TMR is defined for the selected project.
-
In the s50016 Technical Material Requisition screen, in the Technical Material Requisition Header grid, in the General tab, the following exists:
-
The Proc Sch Required checkbox is selected.
-
The value in the MR Revision field is not defined.
-
-
The TMR is not registered on a procurement schedule.
To view unscheduled TMRs
-
Navigate to the s50039 Procurement Status screen.
-
In the Project control block, from the Project dropdown, select the ID of the required project.
-
On the s50039 menu, in the Show Unscheduled group, select TMRs.
The s50016 Technical Material Requisition screen appears.
In the Technical Material Requisition Header grid, a list of unscheduled TMRs for the selected project appears.