Copy a system breakdown structure to a project

  • Last UpdatedMay 07, 2026
  • 2 minute read

Copy a system breakdown structure from a source project to a target project.

  1. Navigate to the s10004 Set-Up Project Structure and Systems screen.

  2. In the Current Project control block, from the Project dropdown, select the ID of the required project.

  3. To refresh the screen, select the F5 key.

  4. On the s10004 menu, in the Actions group, select Copy Systems.

    The d0030 Copy System Structure dialog appears.

  5. From the Target Project dropdown, select the ID of the target project.

    In the Options section, the copy checkboxes are available based on the selected target project.

  6. In the Options section, perform any of the following:

    • To copy the hierarchical system structure to the target project, select the Copy Structure checkbox.

    • To copy all the systems to the target project, select the Copy System Numbers checkbox.

    • To copy the original estimate values of all the systems to the target project, select the Copy Orig Est Values checkbox.

    • To copy the original estimate split values of all the systems to the target project, select the Copy Orig Est Split Values checkbox.

    • To copy the budget values of all the systems to the target project, select the Copy Budget Values checkbox.

    • To copy the budget split values of all the systems to the target project, select the Copy Budget Split Values checkbox.

    • To copy the forecast values of all the systems to the target project, select the Copy Forecast Values checkbox.

    • To copy the forecast split values of all the systems to the target project, select the Copy Forecast Split Values checkbox.

  7. Select Save.

    The s10004 Set-Up Project Structure and Systems screen is refreshed. The Current Project control block is updated with the details of the target project.

    The system breakdown structure is copied from the source project to the target project.