Overwrite a material allocation run
- Last UpdatedMay 07, 2026
- 1 minute read
Overwrite the contents of a material allocation run to determine whether a specific site Material Take-Off (MTO) item is included in or excluded from the material allocation run.
-
Navigate to the s23003 Material Allocation Run screen.
-
In the Current Project control block, from the Project dropdown, select the ID of the required project.
-
To refresh the screen, select the F5 key.
-
In the Material Allocation Run grid, select a row.
-
On the s23003 menu, in the Manage Run group, select MTO Line Item Details.
The d0403 Select line items to include/exclude dialog opens.
-
In the grid, select a row.
-
From the Rule dropdown, select one of the following:
-
Exclude: To exclude a site MTO item from the material allocation run.
-
Include: To include a site MTO item in the material allocation run.
-
-
Select Ok.
The material allocation run is modified.