Copy budget splits from 10007

  • Last UpdatedMay 07, 2026
  • 1 minute read

Copy budget splits to original estimate splits. Before you begin, in the Related Data grid, in the Budget Split tab, in the grid, ensure a record exists.

  1. Navigate to the s10007 Project Cost Account Budget screen.

  2. In the Current Project control, from the Project dropdown, select the ID of the required project.

  3. To refresh the screen, select the F5 key.

  4. In the Levels and Cost Accounts grid, select a row.

  5. In the Cost Accounts grid, select a row.

  6. In the Related Data grid, perform one of the following:

    • To copy budget splits to original estimate splits, perform the following:

      1. Select the Org Est Split tab.

      2. On the s10007 menu, in the Copy/Import Split values group, select Copy Budget.

        The budget splits from the Budget Split tab are copied to the Org Est Split tab.

        In the Org Est Split tab, in the grid, the copied rows appear.

      1. To copy budget splits to forecast splits, perform the following:

        1. Select the FCast Split tab.

        2. On the s10007 menu, in the Copy/Import Split values group, select Copy Budget.

          The budget splits from the Budget Split tab are copied to the FCast Split tab.

          In the FCast Split tab, in the grid, the copied rows appear.

      2. To save the changes, on the Home menu, in the Record group, select Save.