Approve a technical deviation
- Last UpdatedMay 07, 2026
- 1 minute read
Approve a technical deviation to pre-award the request for quote related to the technical deviation in the follow-up process.
-
Navigate to the s20023 Material Substitution and Deviation screen.
-
In the Material Substitution control block, from the Project dropdown, select the required project ID.
-
In the Material grid, select a row.
-
In the Position grid, select the Technical Deviations tab.
-
In the Technical Deviations grid, select a row.
-
On the s20023 menu, in the Workflow group, from the Workflow dropdown, select Approve.
In the General tab, the Approval Status checkbox is selected and the Approved By field is updated for the selected technical deviation.