Update the planning status of a hull unit material list
- Last UpdatedMar 12, 2025
- 2 minute read
Update the planning status of a hull unit material list and control the release of the hull unit material list items for production or procurement.
Prerequisites
Before you begin, complete the following:
-
Ensure you save all the changes in the hull unit material list.
-
To update the planning status to Partly Planned or Totally Planned, ensure you update the Cost Account field (for projects with Use Cost Accounts in Material Control checkbox selected in the s10001 Projects screen) and the System field of all the hull unit material list items.
To update the planning status of a hull unit material list
-
Navigate to the s30000 Hull Unit Material List screen.
-
To refresh the screen, select the F5 key.
-
In the Hull Unit Material List Header grid, select a row.
-
On the s30000 menu, in the Status group, from the Planning dropdown, select one of the following:
-
Not Planned: The hull unit material list is not planned. The hull unit material list items are not available for view in the pallet list and thus not available for addition to the Delivery Request List (DRL) from the s30003 Hull Material Delivery Request List screen.
-
Partly Planned: The hull unit material list is partially planned. The hull unit material list items are available for addition to the DRL from the s30003 Hull Material Delivery Request List screen.
-
Totally Planned: The hull unit material list is totally planned. The hull unit material list items are available for addition to the DRL from the s30003 Hull Material Delivery Request List screen.
-
-
(Optional) To revert the status update, on the s30000 menu, in the Status group, select Revert.
-
To save the changes, on the Home menu, in the Record group, select Save.