Update the actual date of a procurement schedule

  • Last UpdatedMar 12, 2025
  • 1 minute read

Update the Actual Date of a procurement schedule milestone related to an Event.

Prerequisites

Before you begin, complete the following:

  • Ensure you have the Update Schedule and the Write UI right for the s50037 Procurement Schedules screen. For more information, see Assign UI rights to a user role.

  • Ensure the procurement schedule is related to a project component, a Material Requisition (MR), or a Technical Material Requisition (TMR).

  • Ensure the procurement schedule has the required object link to a project component, an MR, or a TMR.

To update the actual date of a procurement schedule

  1. Navigate to the s50037 Procurement Schedules screen.

  2. To refresh the screen, select the F5 key.

  3. In the Procurement Schedules grid, select a row.

    Ensure only one schedule is selected. Ensure the schedule status is Open, Closed or Change.

  4. On the s50037 menu, in the Scheduling group, select Update Actuals.

    The Actual Date is updated. For information on how the actual dates are updated, see Actual date update rule-set.

  5. To save the changes, on the Home menu, in the Record group, select Save.