Update the delivery status of a material
- Last UpdatedMay 07, 2026
- 1 minute read
Update the delivery status of a received material to Completely Delivered, Partially Delivered, or Not Delivered based on the received quantity of the material. You can update the delivery status of a material to Not Delivered only when the value in the Rec Qty field is 0.
-
Navigate to the s60002 Change Goods Receipt screen.
-
Select the PO Search tab.
-
To refresh the screen, select the F5 key.
-
In the Purchase Order grid, select a row.
Ensure the Purchase Order (PO) related to a received material is issued and the delivery status of the PO is Partly Delivered or Completely Delivered.
-
In the Purchase Order Position grid, select a row.
Ensure the delivery status of the PO position is Partly Delivered or Completely Delivered.
-
On the s60002 menu, in the PO Actions group, select Select Purchase Order Position.
-
To refresh the screen, select the F5 key.
In the Receipt Logs tab, the received material appears in the Receipt Transactions grid.
-
In the Receipt Transactions grid, select the required row.
-
On the s60002 menu, in the Delivery Status group, from the Change Delivery Status dropdown, select one of the following:
-
Partially Delivered: To indicate that some quantity from the required quantity of a material is received.
-
Completely Delivered: To indicate that the required quantity of a material is received.
-
Not Delivered: To indicate that the material is not received.
-
-
On the Home menu, in the Record group, select Save.
The delivery status of the material is updated.