Update the change details for a non time-phased project

Update the change details for a non time-phased project

  • Last UpdatedMay 07, 2026
  • 1 minute read

For a project, if the Use time phase budget checkbox is cleared in the s10001 Projects screen, then the project is considered a non time-phased project.

  1. Navigate to the s10010 System Budget Changes screen.

  2. In the Current Project control block, from the Project dropdown, select the ID of the required project.

    Ensure the selected project is a non time-phased project.

  3. To refresh the screen, select the F5 key.

  4. In the Budget Change grid, select a row.

  5. Select the Change tab and perform any of the following as required:

    • In the Material Change field, enter the change that is applied to the material budget. For example, to decrease the approved budget value by 100, you can enter -100 in the Material Change field.

    • In the Sub-Contracts Change field, enter the change that is applied to the subcontracts budget.

    • In the Direct Expenses Change field, enter the change that is applied to the direct expenses budget.

    • In the Man Hour (money) Change field, enter the change that is applied to the man hours budget in terms of money.

    • In the Man Hour (hour) Change field, enter the change that is applied to the man hours budget, specified in hours.

  6. To save the changes, on the Home menu, in the Record group, select Save.