Open the DRL related to a material allocation package

Open the DRL related to a material allocation package

  • Last UpdatedMay 07, 2026
  • 1 minute read

Open the Delivery Request List (DRL) related to a material allocation package in the s21001 Delivery Request Lists screen. You can view all the DRLs that hold items created for any site Material Take-Off (MTO) item related to the material allocation package.

  1. Navigate to the s23002 Material Allocation Package screen.

  2. In the Current Project control block, from the Project dropdown, select the ID of the required project.

  3. To refresh the screen, select the F5 key.

  4. In the Material Allocation Package grid, select a row.

  5. On the s23002 menu, in the Reservations group, from the Reservation Details dropdown, select Goto DRL.

    The s21001 Delivery Request Lists screen appears. In the Delivery Request List grid, view the DRL related to the site MTO included in the material allocation package. In the Line Item grid, view the related DRL items.